Paraguay’s power utility plans 2027 expiry for miners’ special contracts

What happens to miners’ power contracts as demand for Paraguay’s hydroelectricity rises? In a November 14, 2026 report citing CoinDesk, TechFlow said state utility ANDE planned to let all special electricity contracts for crypto miners expire on December 31, 2027. The plan was reported amid growing domestic demand and competition from AI companies for low-cost hydropower.

ANDE projected $350 million in revenue from crypto miners in 2026. As of April, miners had contracted for about 944 MW of power. That is contracted capacity, not a reported measure of electricity consumed.

ANDE engineers also proposed a separate limit starting in 2028: a combined 700 MW for mining, AI and data centers, with power allocated through bidding. That proposal had not been adopted. Meanwhile, Kuntur, a company associated with the Iguazú AI City project, had signed a 15-year supply contract with ANDE for up to 286 MW.